Most planners spend their Monday morning doing the same job: working out which orders still have no production run, finding a free workstation, checking who is in, and moving things around until nothing clashes. ProdaraOS can do the first draft of that for you, and leave the decisions with you.
What the automatic planner does
It starts with every open sales order that has lines with no production run yet. Then, for each product, it proposes a workstation and a team, and places the lines on the calendar, earliest due date first, in the earliest free slot that actually works.
Working out what "actually works" is the hard part. The planner respects:
- factory working days and hours, and bank holidays
- each person's days off, holidays and shifts
- runs already booked on the workstation
- optionally, people who are already booked on another run at the same time
No extra set-up to key in
The workstation and team suggestions come from your own history: the workstation most often used for that product in recent runs, and the team from the latest run on it. Nothing extra to set up, and nothing to enter twice. A product with no history gets a sensible default, so a new line does not block the plan.
The planner shows every proposed run on a review screen and flags lines that would be late or cannot be scheduled. Nothing is written to the calendar until you confirm. You can change the workstation or team for any product before you do.
When a line is going to be late
For lines that would finish after their due date, the planner can search for faster options. It tries adding up to three extra people, or moving the line to a different workstation, and only suggests a change if that line finishes earlier and the rest of the batch is not made later. You see the saving and whether the due date would now be met, and you decide.
Optional rules, all off until you want them
Every rule is off by default, so a new customer's planner behaves simply until they choose otherwise. Switch on what suits your site:
- Changeover gap: time left between two runs on the same workstation for set-up or wash-down.
- Allergen clean-down: extra time when the previous run carries an allergen the next one does not. This uses your allergen matrix.
- Allergen sequencing: among lines due the same day, plan allergen-free products first and allergen-heavy ones last, so fewer clean-downs are needed.
- Shelf-life guard: do not make a product earlier than its shelf life allows, given the share of shelf life your customer expects on delivery.
- Working-hours limits: keep planned shifts inside daily and weekly limits. Read more about this one.
Confirm once, undo in one click
When you confirm, ProdaraOS saves the whole batch in one go and logs each run in the audit trail. An order is marked Scheduled once every line on it has a run. The batch is recorded, so the last schedule can be taken back in one click if you change your mind.
If you prefer, the planner can also schedule the lines that fit on time by itself when Planning opens. Late or problem lines are always left for a person to review, and everything is audit logged and can be undone.
Where it fits
Automatic planning does not replace a planner's judgement about their own factory. It removes the repetitive part, so the time goes on the lines that need a decision. It also sits on the same data as the rest of ProdaraOS, so the schedule knows about your stock, your allergen matrix and your staff.
New to planning in general? Our practical guide to production planning for small food manufacturers covers the fundamentals.
About this guidance. This article is general information for food and feed manufacturers. It is not legal advice and is not a substitute for the standard itself or for advice from your certification body or a SALSA-approved mentor. ProdaraOS supports audit readiness but does not guarantee audit compliance or certification.